eG Monitoring
 

Summary Graph

The summary graph gives an overall picture of the percentage of good, bad and unknown measurements over a period of time and can be obtained by using the Summary option under the Graphs menu. To view a summary graph, do the following:

  • The service for which the graph is to be plotted can be selected from the Service list box. The Component list box gets populated with all the components associated with this service. However, this step is optional. If the user does not select a service, all the components in the infrastructure that are currently being managed by the eG manager will be listed in the Component list box. 

  • Next, a specific component associated with this service can be selected from the Component list box. You can even narrow your component-search further by specifying the whole/part of a component name in the Filter By text box here. All components with names that embed the specified search string will then populate the Component list, thus making it easier for you to pick a component.

  • All the layers that map to the selected component will be available in the Layer list box and the user can choose any layer.

  • The tests corresponding to the layer under consideration form the options of the Test list box. The required test can be chosen from this box.

  • If the chosen test is being executed by more than one measurement host, then the Msmt Host list gets populated with all such measurement hosts. From this list, select the measurement host for which the graph is to be generated.

  • The measurements reported by the selected test appear in the Measure list box, one of which can be picked.

To override the default settings of the Summary Graph, click on the icon. The Settings pop-up window appears:

  • Users can also opt to view the hourly, daily or monthly variations of measures in the case of summary graphs by selecting an appropriate option from the Duration list box.

  • The period for which the variations of the selected measurements have to be analyzed can be specified using the Timeline list. You can either provide a fixed time line such as 1 hour, 2 days, etc., or select the Any option from the list to provide a From and To date/time for graph generation.